Gile Road – Complete reconstruction of 3500 feet and apply Base coat of pavement.
Case Road – Reclaim 2000 feet from the intersection with Mill Pond Road rework as needed and apply Base coat of pavement.
McCrillis Road – Reclaim 800 feet along river from hydrant toward bridge and apply Base coat. Overlay entire length of road.
East and West Kelsey Roads – Reclaim old surface, rework as needed, apply Base coat.
South Summer Street – Reclaim 1700 feet and apply Base coat.
Canton Court – Overlay
The work shall be done in June, July and August.
Work shall be completed as the budget allows.
Mill Pond Bridge will be CLOSED July 11, 2005 through August 19, 2005.
This work will be performed by outside contractors.
|